Requires certain construction project contracts with a value of greater than or equal to five million dollars to include siting of renewable energy systems, qualified energy storage systems, or major electric transmission facilities.
Requires renewable energy data resources provided by NYSERDA to include mapping of certain capital projects with a value of greater than one million dollars for purposes of providing public information on the viability of siting of solar energy arrays, major renewable energy facilities, or major electric transmission facilities.
Requires renewable energy data resources provided by NYSERDA to include mapping of certain capital projects with a value of greater than one million dollars for purposes of providing public information on the viability of siting of solar energy arrays, major renewable energy facilities, or major electric transmission facilities.
Relates to qualified energy storage systems; authorizes energy storage permitting under the office of renewable energy siting and electric transmission.
Authorizes municipalities to require a permit for the construction of a major renewable energy facility, major electric transmission facility or certain major electric generating facilities.
Authorizes municipalities to require a permit for the construction of a major renewable energy facility, major electric transmission facility or certain major electric generating facilities.
Authorizes ORES to issue siting permits for battery energy storage systems for use by data centers, regardless of the expected storage or transmission capacity of such battery energy storage systems, and whether or not such battery energy storage systems will be co-located with renewable energy systems; requires data centers to submit carbon reduction plans.
Requires the office of renewable energy siting and electric transmission to establish and/or amend rules and regulations pertaining to standards related to the siting, design, construction and operation of major renewable energy facilities; requires such rules and regulations to include information relating to certain definitions, preapplication procedures, application procedures, farmland conservation fees, and farmland protection; provides for the repeal of such provisions upon expiration thereof.
Requires the office of renewable energy siting and electric transmission to establish and/or amend rules and regulations pertaining to standards related to the siting, design, construction and operation of major renewable energy facilities; requires such rules and regulations to include information relating to certain definitions, preapplication procedures, application procedures, farmland conservation fees, and farmland protection; provides for the repeal of such provisions upon expiration thereof.
Relates to transparency and other requirements for applications submitted to ORES for siting of major renewable energy and major electric transmission facilities.